Keywordshospital fit-out planningproject decision sequencemedical door specificationshielding designoperating room planning
The wall and the shielding come first
Two decisions sit at the top of the sequence.
The wall build-up decides what every frame in the room has to suit, and the shielding calculation decides the lead equivalent every item on the boundary has to carry. Getting these two settled first means the door, the wall panels, the window and the penetrations can all be made to one set of figures instead of being adjusted one against another.
Then doors, then the ceiling grid
Doors follow the wall, because a frame is made to the build-up. The ceiling grid comes next, since the modular wall panel module and the ceiling module are set out together, and the lighting layout follows the grid.
Decide the ceiling last and the light fittings have to be sized to whatever space is left, rather than to the room's lighting requirement.
Prompthospital construction site with steel stud wall framing and a shielding drawing pinned nearby, early fit-out stage, natural light industrial photography
ShotEarly fit-out stage, with the wall build-up being set out.
Product03.2 Modular Operating Room Panels
Promptsuspended cleanroom ceiling grid under installation with LED panel lights being positioned, healthcare construction, overhead industrial photography
ShotCeiling grid and light positions being set out to the wall module.
Product03.5 Cleanroom LED Panel Lights
Equipment and storage at the end
- Operating tables, lamps, cabinets and scrub stations are decided once the room's geometry is fixed.
- Their positions depend on the door swing, the ceiling layout and the service outlets in the wall — all of which are settled by then.
- Choosing equipment before the room is set out is the most common cause of a cabinet that does not fit the wall it was bought for.
