Custom work is the first variable

A standard leaf and a leaf made to a project's wall build-up have different lead times.

Production starts after the drawing is approved, and for custom doors, shielding and operating room panels, that drawing is only settled once the schedule, the wall detail and the shielding calculation are all in. The time spent before the drawing is approved is usually longer than the time spent making the item.

Finishing and coating

Powder coating has its own cycle. The colour is applied after forming, and a project-specific colour adds a matching stage that a standard colour does not need.

On a large order this is a batch process, so a late colour decision holds up a whole batch rather than one door. For shielding materials, the equivalent step is cutting to the lining plan, which cannot start before the plan is issued.

Image 1 — placeholder

Promptsheet metal fabrication workshop, worker measuring a steel door panel against a technical drawing, sparks and machinery in background, industrial photography

ShotA custom door leaf being made against an approved drawing.

Product01.2 Automatic Sealed Sliding Doors

Image 2 — placeholder

Promptpowder coating line in a factory, steel door panels hanging on a conveyor entering a coating booth, clean industrial process photography

ShotDoor leaves on a coating line, batched by colour.

Product01.4 Steel Cleanroom Doors

Packing, shipping and site readiness

  • Once goods are made, the remaining variables are packing, transit and whether the site can receive them.
  • Crating for long sea freight takes longer than palletising for a local delivery, and the site has to have somewhere dry to store doors and shielding before the rooms are ready.
  • Where a programme is tight, splitting the order so that lining material arrives before doors is often faster than waiting for one complete shipment.